Ashuganj 225 MW Combined Cycle Power Plant
Work Description:
1. Piling Works
2. Temporary Works
3. Civil & Building Works
4. C. W Intake System Works
Work Description:
1. Piling Works
2. Temporary Works
3. Civil & Building Works
4. C. W Intake System Works
Work Description:
1. Intake System Works
2. Civil & Deep Tube Well Works
Work Description:
Construction of 150 MW Power Plant
Work Description:
1. Gas Turbine Building
2. Gas Turbine Foundation
3. Steam Turbine Building & Foundation
4. Chemical Dosing Shelter
5. Service Gas Shelter
6. Watch Tower
7. Fuel Gas Compressor
8. Electrical Building
Work Description:
Construction of 70 MW Peaking Power Plant (Total Civil Works)
Work Description:
1. Sub-soil Investigation Work
2. Construction of Pile Testing
3. Construction of 2nd Level Over Existing BPDB Rest House Building
4. Construction of Cast in Situ RCC Piling Work