Haripur 360 MW Power Plant

Categories: All, Power Plant
Project Nature: Power Plant
Value: 421.13 Million BDT
Project Schedule Date: Start: 2009-12-25 Finish: 2014-05-30
Project Location: Haripur, Narayanganj
Project Status: Completed
Client Name: Electrical Generation Company of Bangladesh Limited

Work Description:
1. Gas Turbine Building
2. Gas Turbine Foundation
3. Steam Turbine Building & Foundation
4. Chemical Dosing Shelter
5. Service Gas Shelter
6. Watch Tower
7. Fuel Gas Compressor
8. Electrical Building